__________ involves using project characteristics in a mathematical model

__________ involves using project characteristics in a mathematical model

A.
Analogous estimating

B.
Life-cycle costing

C.
Parametric modelling

D.
Bottom up estimating

Explanation:
Parametric modeling : Using project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot).