In order to determine the impact of the requested change, you will need a work breakdown structure,

You are project manager of a project. A customer requests a scope change in the project . In order to determine the impact of the requested change, you will need a work breakdown structure, change request, scope management plan, and:

A.
Performance reports.

B.
A responsibility matrix.

C.
A Pareto diagram

D.
A Monte Carlo simulation.