In general, attempts to smooth out period to period resources will _____ the scheduled time and ____ admin 11 years ago In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. A.Increase, increase B.Decrease, decrease. C.Increase, decrease. D.Increase, increase or decrease. E.Decrease, increase. ← Previous question Next question →