If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?
A.
0-413
B.
0-82
C.
1-06
D.
1-142
Explanation:
Cost Performance Index (CPI): The ratio of budgeted costs to actual costs (BCWP / ACWP). If CPI is less than 1, this means that the project is over budget.