PMI Exam Questions

If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?

If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?

A.
0-413

B.
0-82

C.
1-06

D.
1-142

Explanation:
Cost Performance Index (CPI): The ratio of budgeted costs to actual costs (BCWP / ACWP). If CPI is less than 1, this means that the project is over budget.