Identification of Mandatory Dependencies is done during which of the following process: seenagape 13 years ago Identification of Mandatory Dependencies is done during which of the following process: A.Sequence Activities B.Develop Schedule C.Define Activities D.Estimate Activity Durations ← Previous question Next question →