How should a stakeholder who is classified as high power and low interest be grouped in a power/inte

How should a stakeholder who is classified as high power and low interest be grouped in a
power/interest grid during stakeholder analysis?

A.
Keep satisfied

B.
Keep informed

C.
Manage closely

D.
Monitor