how much will be left in the contingency reserve?

You are the project manager of the HJH project for your company. In your project, you have
created the probability-impact risk matrix as shown in the following figure:

If Risk D happens in this project, how much will be left in the contingency reserve?

A.
$440,000

B.
$233,500

C.
$258,500

D.
$243,500