PMI Exam Questions

how many weeks is the expected duration of the activity?

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the
worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.
One

B.
Five

C.
Six

D.
Seven