How many risk response types are available for a negative risk event in the project?

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your
project with your team. How many risk response types are available for a negative risk event in the
project?

A.
Four

B.
One

C.
Three

D.
Seven