PMI Exam Questions

how many months is the expected activity duration?

Using the three-point estimating technique, if the most likely duration is four
months, the optimistic duration is two months, and the pessimistic duration is one
year, how many months is the expected activity duration?

A.
Two

B.
Four

C.
Five

D.
Twelve