How is the process of collecting requirements defined?

How is the process of collecting requirements defined?

A.
Defining and documenting project sponsors’ needs to meet the project objectives

B.
Defining and documenting stakeholders’ needs to meet the project objectives

C.
Defining and documenting the project teams’ needs to meet the project objectives

D.
Defining and documenting the project needs to meet the project objectives