Given the following values, what is the calculated expected activity cost (CE) when using PERT? admin 11 years ago Given the following values, what is the calculated expected activity cost (CE) when using PERT? CO = $7,000 CM = $10,500 CP = $11,000 A.$ 4,750 B.$ 9,500 C.$10,000 D.$11,500 ← Previous question Next question →