Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what i admin 11 years ago Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average? A.6.1 B.6.3 C.6 D.4 ← Previous question Next question →