Function of the __________ is to make sure that changes to anything in the project are recorded and

Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.

A.
Project Manager

B.
Sponsor

C.
Team Lead

D.
Management

Explanation:
Function of the project manager is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.