From a buyer’s standpoint, which of the following is true?

From a buyer’s standpoint, which of the following is true?

A.
Procurement planning should include consideration of potential subcontracts.

B.
Procurement planning does not include consideration of potential subcontracts since this is the duty of the contractor.

C.
Subcontractors are first considered during the Solicitation Process.

D.
None of the above