PMI Exam Questions

Formal written correspondence with the customer is required when:

Formal written correspondence with the customer is required when:

A.
Defects are detected.

B.
The customer requests additional work not covered under contract.

C.
The project has a schedule slippage that includes changes to the critical path.

D.
The project has cost overruns.