Formal acceptance by the client or sponsor of the project should be prepared and distributed during

Formal acceptance by the client or sponsor of the project should be prepared and distributed during which process?

A.
Distribute Information

B.
Administrative Closeout

C.
Organizational Planning

D.
Report Performance