Deflection or transfer of a risk to another party is part of which of the following risk response ca

Deflection or transfer of a risk to another party is part of which of the following risk response categories?

A.
Transfer

B.
Acceptance

C.
Avoidance

D.
Mitigate

Explanation:
A is the correct answer. transfer of a risk to another party (third party) is part of Transfer strategy (Strategies for negative risks).