PMI Exam Questions

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are example

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.

A.
Enterprise benefits measurement methods when selecting a project

B.
Integral parts of the SOW

C.
Ways to ensure stakeholder commitment

D.
Project selection methods

Explanation:
Projects are seeded from the recognition of a regulatory or business need. Cost benefit analysis, scorecard modelling , payback periods, and internal rate of return are examples of benefits measurement methods when selecting a project. Best Option is A.