Conditions that are not under the control of the project team that influence, direct, or constrain a seenagape 9 years ago Conditions that are not under the control of the project team that influence, direct,or constrain a project are called: A. Enterprise environmental factors B. Work performance reports C. Organizational process assets D. Context diagrams ← Previous question Next question →