PMI Exam Questions

Collect Requirements is:

Collect Requirements is:

A.
Developing a comprehensive plan based on input from major stakeholders

B.
The process of defining and documenting stakeholders needs to meet project objectives

C.
The process which provides information for planning project milestones

D.
Subdividing the project into smaller, more manageable components

Explanation:
Collect Requirements : The process of defining and documenting stakeholders needs to meet project objectives