Which type of dependency is established based on knowledge of best practices within a particular app

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a

specific sequence is desired, even though there may be other acceptable sequences?

A. External

B. Internal

C. Mandatory

D. Discretionary