Which tool or technique of the Define Activities process allows for work to exist at various levels

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on

where it is in the project life cycle?

A. Historical relationships

B. Dependency determination

C. Bottom-up estimating

D. Rolling wave planning