PMI Exam Questions

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Which Project Time Management process includes bottom-up estimating as a tool or technique?

A.Estimate Activity Resources

B.Sequence Activities

C.Estimate Activity Durations

D.Develop Schedule