Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A.Estimate Costs
B.Estimate Activity Resources
C.Control Costs
D.Determine Budget
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A.Estimate Costs
B.Estimate Activity Resources
C.Control Costs
D.Determine Budget