Which process in Project Time Management includes reserve analysis as a tool or technique?

Which process in Project Time Management includes reserve analysis as a tool or technique?

A. Estimate Activity Resources

B. Sequence Activities

C. Estimate Activity Durations

D. Develop Schedule