PMI Exam Questions

Which Process Group and Knowledge…

Which Process Group and Knowledge

Area include the Sequence Activities process?

A. Executing Process Group and Project Time Management

B. Executing Process Group and Project Cost Management

C. Planning Process Group and Project Time Management

D. Planning Process Group and Project Cost

Management