PMI Exam Questions

Which output of Project Cost Management consists of quantitative assessments of the probable costs r

Which output of Project Cost

Management consists of quantitative assessments of the probable costs required to complete project work?

A.Activity cost estimates

B.Earned value management

C.Cost management plan

D.Cost baseline