PMI Exam Questions

Which of the following schedule network analysis techniques is applied when a critical path method c

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is

critical?

A.Applying calendars

B.Resource leveling

C.Resource planning

D.Resource conflict management