Which of the following is an output of the Conduc
t Procurements process?
A.Project statement of work
B.Selected sellers
C.Risk register updates
D.Teaming agreements
Which of the following is an output of the Conduc
t Procurements process?
A.Project statement of work
B.Selected sellers
C.Risk register updates
D.Teaming agreements