Which of the follow
ing factors is lowest at the start of the project?
A.Cost of changes
B.Stakeholder influences
C.Risk
D.Uncertainty
Which of the follow
ing factors is lowest at the start of the project?
A.Cost of changes
B.Stakeholder influences
C.Risk
D.Uncertainty