Which is the correct formula for calculating expected activity cost for three-point estimating?
A.Ce = (C0 + 6Cm + Cp)/4
B.Ce = (6C0 + Cm + Cp)/4
C.Ce = (C0 + 4Cm + C
p)/6
D.Ce = (C0 + C-ž, + 4Cp) / 6