PMI Exam Questions

When an activity cannot be estimated with a reasonable degree of confidence, the work within the act

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.Bottom-up

B.Parametric

C.Analogous

D.Three-point

QUEST