What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and th
e earned value (EV) is $50?
A. 0.50
B. 0.67
C. 1.50
D. 2.00
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and th
e earned value (EV) is $50?
A. 0.50
B. 0.67
C. 1.50
D. 2.00