PMI Exam Questions

The Project Human Resource Management process that involves confirming human resource availability a

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.Acquire Project Team.

B.Plan Human Resource Management.

C.Manage Project Team.

D.Develop Project Team.