The process of identifying and documenting relationships among the project activities is known as:
A. Control
Schedule.
B. Sequence Activities.
C. Define Activities.
D. Develop Schedule.
The process of identifying and documenting relationships among the project activities is known as:
A. Control
Schedule.
B. Sequence Activities.
C. Define Activities.
D. Develop Schedule.