The correct equation for schedule variance (SV) is earned value:

The correct equation for schedule variance (SV) is earned value:

A.minus planned value [EV – PV].

B.minus actual cost [EV – AC].

C.divided by planned value [EV/PV],

D.divid

ed by actual cost [EV/AC].