In which process might a project manager use risk reassessment as a tool and technique?

In which process might a project manager use risk reassessment as a tool and technique?

A.Perform Qualitative Risk Analysis

B.Monitor and Control Risk

C.Monitor and Control Project Work

D.Plan Risk Responses