If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and t

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.One

B.Five

C.Six

D.Seven