PMI Exam Questions

At the completion of a project, a report is prepared that details the outcome of the research conduc

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A. Result

B.

Product

C. Service

D. Improvement