PMI Exam Questions

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total proje

As part of

a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.BAC

B.EAC

C.ETC

D.WBS

Topic 4, Volume D