After Define Activities and Sequence Activities, the next process is:
A.Estimate Activity Resources.
B.Estimate Activity Durations,
C.Develop Schedule.
D.Control Schedule.
After Define Activities and Sequence Activities, the next process is:
A.Estimate Activity Resources.
B.Estimate Activity Durations,
C.Develop Schedule.
D.Control Schedule.