When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.divided among each of the phases or subprojects.

B.repeated for each of the phases or subprojects.

C.linked to specific

phases or subprojects.

D.integrated for specific phases or subprojects.