Budgets reserved for unplanned changes to project scope and cost are: seenagape 10 years ago Budgets reserved for unplanned changes to project scope and cost are: A.Contingency reserves. B.Management reserves. C.Authorized budgets. D.Cost baselines. ← Previous question Next question →