An input to the Estimate Activity Resources process is: seenagape 8 years ago An input to the Estimate Activity Resources process is: A. Activity resource requirements. B. Published estimating data. C. Resource calendars. D. Resource breakdown structure (RBS). ← Previous question Next question →