An approved change request is an input to which of the following processes?

An approved change request is an input to which of the following processes?

A.
Define Scope

B.
Verify Scope

C.
Monitor and Control Project Work

D.
Integrated Change Control

Explanation:
A is the correct answer. And approved change request input to Define Scope.