PMI Exam Questions

An activity that consumes no time or resource and shows only that a dependency exists between two ac

An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:

A.
A milestone

B.
A hammock

C.
A dummy activity

D.
a and c