A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not c

A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.

A.
Event.

B.
Activity

C.
Correlation

D.
Event constrained within planned effort.

E.
Constant