After Define Activities and Sequence Activities, the next process is: seenagape 10 years ago After Define Activities and Sequence Activities, the next process is: A.Estimate Activity Resources. B.Estimate Activity Durations, C.Develop Schedule. D.Control Schedule. ← Previous question Next question →