After Define Activities and Sequence Activities, the ne… seenagape 8 years ago After Define Activities and Sequence Activities, the next process is: A. Estimate Activity Resources. B. Estimate Activity Durations, C. Develop Schedule. D. Control Schedule. ← Previous question Next question →